Since May 27, 2022, traffic has been rolling past the town through the two tubes. A bypass is being built for 228 million euros, and traffic is then redirected through the town.

Mayor Peter Imminger believes this is the only right path for his community. The State Building Authority wanted to have found a solution by the first maintenance in spring 2023, or at the latest by the second in autumn. But now all the preparatory work should be done. An engineering office is currently preparing the tender, and Schulte wants to place the order for the conversion as soon as possible. This is expected to last six months, followed by a one-week test phase. In an emergency, the ventilation system must automatically recognize in which direction it needs to blow smoke. This can apparently be solved – through some operational, structural, and software-based changes. The biggest challenge was the flow behavior of the smoke gases in the event of a fire. The search for it dragged on.