Masterpiece of drinking water construction: Even the expert is amazed

2022-05-15T06:08:46.627Z


Masterpiece of drinking water construction: Even the expert is amazed Created: 05/15/2022, 08:00 By: Bernhard Jepsen This is what it looks like inside the new Peissenberger elevated tank. The photo shows Georg Haser (left) and Christoph Reichhart (right) in front of one of the two stainless steel tanks. © Photo: Jepsen Actually, the new elevated tank on the "Schweiber" below St. Michael was su


Masterpiece of drinking water construction: Even the expert is amazed

Created: 05/15/2022, 08:00

By: Bernhard Jepsen

This is what it looks like inside the new Peissenberger elevated tank.

The photo shows Georg Haser (left) and Christoph Reichhart (right) in front of one of the two stainless steel tanks.

© Photo: Jepsen

Actually, the new elevated tank on the "Schweiber" below St. Michael was supposed to go into operation this spring.

But the completion of the project, which is estimated at around two million euros, will be delayed by a few weeks.

One of the reasons: the incoming and outgoing lines had to be replanned.

Peißenberg

- Yes, it's a slightly larger Stadl.

Nevertheless, the new elevated tank looks relatively inconspicuous from the outside.

The dimensions of the future core of Peißenberg's drinking water supply only become really clear inside the timber construction.

There, two hygienically self-contained stainless steel tanks, eight meters high and designed with a diameter of 13 meters, were welded together.

An impressive picture for the layperson - but not only for the expert, but also for the specialist: "We were amazed at first," says Christoph Reichhart, a municipal utility worker.

And his boss, Georg Haser, agrees: "In reality, everything looks very different than on the plan.

Much bigger,” explains Peißenberg's water master.

The two stainless steel tanks, each with a capacity of 1100 cubic meters, will replace the old elevated tank from the 1970s.

Actually, the replacement should have already happened according to the original schedule.

But there have been delays.

There was a risk that the pipe would get stuck

So far, everything has gone smoothly on the construction of the elevated tank itself.

"We're on our last legs," reports Haser.

Only with the electronic components is there still a bit of a problem: "Because of Corona, the companies currently have hardly any people left," says Haser.

But that's not the main reason for the shifts in schedule.

The design for the new construction of the inlet and outlet lines caused major problems.

The existing piping of the old drinking water reservoir is being shut down because it is prone to breaks and other faults after more than 50 years of operation.

The plan was to drill a flushing bore on the slope above the western section of the St. Michelsweg up to the new elevated tank at the "Schweiber".

"That was the preferred option, because we wanted to keep the impact on nature to a minimum," explains Haser.

But the changing geological sections, some with massive layers of rock along the planned route, ruined the project.

"The resistance would have been too high and the tube would have been stuck," Haser states.

An open construction brought the desired solution

After examining other alternative methods, the municipal works ultimately decided to have the pipes laid up the slope using the cut-and-cover method.

There are three lines in total.

Namely the inlet from the drinking water well near the Böbinger Ammerbrücke, a bottom outlet pipe and the outlet into the Peißenberg drinking water network.

The open construction requires a high level of technical effort.

A walking excavator was requested by a specialist company from the Zillertal for the earthworks.

A swath in the forest could not be avoided, but will be reforested

Another downer is the interference with nature.

A path had to be cut into the wooded slope from the Michelsbach.

To protect the pipes, it will not be reforested after the construction work.

Laterally positioned tree planks should prevent the slope from slipping.

Haser is happy that the landowner played along: “He was absolutely understanding.

He immediately recognized the importance of the project.”

For Haser, the construction of the new elevated tank is a "stressful time".

But his employees get a lot of praise from their boss: "Without my team, nothing works.

That's perfect.” The new elevated tank is scheduled to go into operation at the end of June or beginning of July.

For Haser and his employees, things are a little more relaxed: "The new elevated tank will last around 100 years," says the water manager.

Weilheim-Penzberg newsletter

: Everything from your region!

Our Weilheim-Penzberg newsletter keeps you regularly informed about all the important stories from the Weilheim and Penzberg region.

Sign up here.

By the way:

Everything from the region

is now also available in our regular Schongau newsletter.

Source: merkur

All news articles on 2022-05-15

You may like

News/Politics 2024-03-27T17:24:39.069Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.