First liners will be able to connect to the electricity network from 2025 thanks to insulated sockets. It accompanies a complete overhaul of the cruise terminal and its three quays which must be completed in 2026.

The connection to the public distribution network by Enedis is completed. It required the creation of 3 km of underground network for an investment of 5.6 million euros. This week, the second phase began with the launch of work to create a distribution station from which a network of buried cables will be installed.