Gipuzkoa takes the lead in Basque high speed. The Basque Government concludes the branch of this territory after 16 years of works and an investment of 1,948 million euros.

34 tunnels (the longest is six kilometers long) and 31 bridges have been built. According to the latest forecasts, ratified today by the counselor, the TAV could be operational in Euskadi in 2027 on its core network. The deadlines will be extended to complete the train accesses to Bilbao and Vitoria.