Bridge: target 5 more bays at 31/12

2019-12-05T16:35:42.048Z


The new bridge spans will be 8 out of 19, mounted by December 31st. Of these 3 have already been launched from October 1 to today. (HANDLE)


(ANSA) - GENOA, 5 DEC - There will be 8 out of 19 total new bridge spans installed by 31 December. Of these 3 have already been launched from October 1 to today. The certainty of the new medium-term objective, which undermines what the Commissioner and Mayor of Genoa, Marco Bucci, hoped to have seen all of them by the end of the year, will only happen on Wednesday, when the manufacturers will present an updated plan to the commissioning structure. At the moment the work on raising the batteries is respected. Those already ready to support new parts of the bridge are the 3rd and 4th along with the 7 and 8 western docks, the 14 and 15 on the east side. On the ground silavora assembling two 50-meter bays and a 100-meter one, but so that the progress of the work does not slow down with respect to the inauguration target in April 2020, it will be necessary to work simultaneously on a greater number of components that have not yet arrived from Fincantieri. That's what the ANSA learns.

Source: ansa

All life articles on 2019-12-05

You may like

News/Politics 2024-03-26T06:35:03.137Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.