Last updated: 2020-02-28 17:38MTR announced today (28th) that the latest cost estimate for the Shazhong Line is HK $ 82.993 billion, which is an increase of HK $ 12.172 billion from the original estimate of HK $ 70.827 billion, which is less than the estimated increase of approximately 16.5 billion issued in December 2017.
MTR also said that the cost estimate was lowered than announced in December 2017 because of the implementation of strict cost control and the continuous progress of the midline-related projects since December 2017. Therefore, there is a greater degree of certainty about the cost.
[Sand Central Line] Hearing Completion Hearing Committee Attorney: Government Expert Opinion Is Speculation
[Sand Central Line] MTR Lawyer Approves Government Expert Opinion Conservative Committee Should Not Accept Its Opinion
[Sand Central Line] Government Counsel: If the ruling of structural safety must assume that engineering problems do not pose a danger