The third runway at Munich Airport remains on the agenda - at least in theory.
As expected, an application by the Greens to irreversibly repeal the building law in the Bavarian state parliament failed.
The plans for a third runway at Munich Airport * have not yet died.
The application by the Greens was rejected.
Only the SPD supported the eco party.
Munich
- The
construction of the 3rd runway
is further away than ever - at the moment even the two existing runways are far from being used to full capacity.
And
Prime Minister Markus Söder
(CSU) has made it clear that construction - as long as he is in charge - will not be tackled.
Assuming his re-election, that would be until
2028
.
But concrete steps to lift the building law are not being taken.
In the
transport committee of the state parliament
, the Freising Green MP Johannes Becher failed with the application to take the railway out of the state
development program
(LEP).
There, the construction of the 4000 meter long runway is still defined as the “goal”.
Airport: Munich hub must be preserved
The governing coalition of the
CSU
and
Free Voters
would like to leave it that way for the time being.
It makes no sense to
make an individual change
in the
LEP
, said the MP Manfred Eibl (FW).
The CSU MP Jürgen Baumgärtner also said that there was “now no reason
to bury
the
3rd Bahn *
in its entirety”.
Baumgärtner made no secret of the fact that he viewed the railway skeptically.
Of course it is "a climate issue".
The aim must be
to reduce
domestic German air traffic
and thereby free up capacity.
A
hub in Munich
must be preserved.
Baumgärtner, however, viewed the building law quite critically.
"There must be no perpetual and permanent building law."
The question of building law, it became clear in the committee, is legally controversial.
In the
runway planning approval decision
, not only the train itself, but also some other construction projects such as the
S-Bahn ring closure
in the area of the
airport
are dealt with.
Since the construction of this railway tunnel has already begun, the question arises whether the building decision can be overturned in its entirety.
The Green MP Becher has made a state parliament request, the answer is pending.
Ultimately, only the SPD took the side of the Greens.
Natascha Kohnen demanded that the
third runway be
"completed administratively".
But the CSU, FW, FDP and AfD had a different opinion.
The
runway
remains "in the freezer", as Becher put it.
Arithmetic games on the capacity of Munich Airport
How many flights are
possible
at Munich Airport *
per year
?
This is a very theoretical question at the moment, because the airport is far from being fully occupied.
But the
Bavarian Ministry of Transport came up
with new figures in the state parliament.
If you assume 90 flights per hour in the
2-lane system
, you end up with a “theoretical capacity” of
480,000 flights per year
, calculated a ministry employee in the transport committee.
But this “theoretical capacity” is never achievable in practice because the utilization is not
the
same for
every
operating hour of the airport
.
This results in a "practical capacity" of
430,000 flights
.
Curious, however: in 2007 and 2008 the
airport
had already exceeded this capacity - with 432,000 flights each year.
The Green MP Johannes Becher also took critical note of the number.
In the
judgment of the
administrative court
, which had dismissed all lawsuits against the expansion, a figure of 480,000 was named as "practicable capacity".
At the moment it's all just gray theory anyway.
According to air traffic control, there have only been
a total of
133,000 flights in
2020
, and by the end of the year there could only be 200,000.
* Merkur.de is part of the Ippen-Digital-Netzwerk.
Construction of Munich Airport * began 40 years ago.
It took twelve years to complete.