Al-Hasakah-Sana
The maintenance workshops of the General Electricity Company of Hasakeh have completed the repair of the malfunction of the 230 KV line connecting Tabqa and the doors.
In a statement to SANA's correspondent, the general manager of the company, Eng. Anwar Akla, pointed out that the return of the 230 kV tension line to the doors to service came after repairing the malfunction in the area between the villages of Makhroum and Souda in the southwestern countryside of Hasaka. Before the company.
Okla explained that the workshops completed the repair of the Tel Baidar tension line, 20 KV, in the northwestern countryside of Hasaka. The repair operations included the erection of two columns and the complete complement at the Tel Irfan junction and restoring the line to service.
The amount of energy received via the 230 kV line of the doors class is 70 Mega.