Repairing emergency breakdowns on the electrical network in Latakia as a result of the Israeli aggression

2021-05-06T04:42:31.527Z


Lattakia-SANA The General Electricity Company of Lattakia Governorate completed the repair work for the faults caused by the enemy


Latakia - Sana

The General Electricity Company of Lattakia Governorate completed the work of repairing faults caused by the Israeli aggression at dawn today, when a group of medium voltage lines went out of service in the Al-Haffah area.

The general manager of the company, Engineer Jaber Asi, explained that the medium voltage lines “Sarna-Bashmana-Slanfeh” were out of service, which led to power cuts to the villages that feed from these lines, including the Jorin water pump line that feeds the Slanfeh area with water.

Assi pointed out that electricity was also cut off in the Friday Market area in Lattakia, as a result of shrapnel left by the aggression on the network and its fall to the ground.

Assi pointed out that the company's workshops went immediately to the places where the damage occurred and began their work until the completion of the repair of the faults and the restoration of electricity to the aforementioned areas.

The air defense media in the Syrian Arab Army confronted at dawn today an Israeli aggression from the direction of southwest Lattakia on some points in the coastal area, and some of the aggression's missiles were dropped.

Source: sena

All news articles on 2021-05-06

You may like

News/Politics 2024-04-08T14:05:05.427Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.