Tunma Line | The guild decides to build the Hung Shui Bridge station to be completed in 2030, the residents of the new district will have no rail connection for 6 years

2021-05-29T05:39:50.496Z


Hung Shui Bridge/Xia Village New Development Zone, the first batch of residents are expected to be occupied in 2024. Passed by the Chief Executive in Council, inviting MTR to carry out the detailed planning and design of Hung Shui Kiu Station. Construction is expected to start in 2024.


Social News

Written by: Zhong Yan

2021-05-27 17:57

Last update date: 2021-05-27 17:58

Hung Shui Bridge/Xia Village New Development Zone, the first batch of residents are expected to be occupied in 2024.

The Chief Executive in conjunction with the Executive Council approved the invitation to MTR to carry out the detailed planning and design of the Hung Shui Kiu Station. Construction is expected to start in 2024. The project is expected to take 6 years to complete by 2030.

That is to say, the first batch of 4,400 residents in the new development zone will face the situation of no rail connection in the first 6 years of their occupation.

The MTR expressed that it welcomes the government to start the detailed planning and design work of the Hung Shui Kiu Station project, and indicated that it will start the consultancy tendering process immediately.

Preliminary conceptual scheme of Hongshuiqiao Station.

(Railway Development Strategy 2014)

The Hong Kong Government announced that it has invited the MTR to carry out the detailed planning and design of the Hung Shui Kiu Station, and will negotiate with the MTR Corporation the financial arrangements for the project to add a new railway station between the existing West Rail Line Tin Shui Wai Station and Siu Hong Station. Take care of the transportation needs of the Hung Shui Bridge/Xia Village New Development Area in the future.

The government expects that the construction of the Hung Shui Kiu Station on the Tuen Ma Line will start in 2024, and it will take 6 years to complete in 2030 to meet the development plan of the Hung Shui Kiu/Xia Village New Development Area.

The government expects that the Hung Shui Bridge Development Area will gradually move in from 2024 residents.

(Profile picture / Photo by Gong Hui)

The economic benefit of Hongkong Bridge Station Project is estimated to reach 55 billion yuan

A spokesperson for the Transport and Housing Bureau said that it currently takes about 24 minutes to reach Tin Shui Wai Station from the city centre of the future new development area and 20 minutes to Siu Hong Station. After Hung Shui Kiu Station is available, it will take two stations to Hung Shui Kiu City Centre. Each takes only about 4 minutes.

The Transportation and Housing Bureau estimates that during the 50-year operation period of the Hung Shui Bridge Station, the economic benefits of the Hung Shui Bridge Station are estimated to be 55 billion yuan at 2018 prices, including the time value of approximately 314 million hours saved for the public.

The government estimates that the Hung Shui Bridge/Xia Village New Development Area can accommodate 218,000 people, of which 176,000 are new populations and 150,000 new jobs.

According to the document submitted by the Development Bureau to the Public Works Subcommittee of the Legislative Council in May last year, it is estimated that the first batch of residents will be occupied in 2024, and the first phase of the development will build about 1,300 dedicated resettlement housing units in phases and 3 rural relocations. The 100 households accommodated on the site, that is, a total of 1,400 households, have a population of 4,400.

The second phase of the Hung Shui Bridge development is also expected to be completed in 2032. There will be 30,900 units and 90,800 people living in by then.

Suggestions on the alignment of environmental transport services in the Hung Shui Bridge/Xia Village New Development Zone.

(Picture of Civil Development Engineering Office)

Therefore, according to the current timetable set by the government, the Hung Shui Bridge Station will not begin construction until the first batch of residents enter the occupation in 2024, and it will wait six years for railway connections.

The government also plans to build an environmentally friendly transportation service to connect Hung Shui Kiu and Yuen Long South Development Area, and select an automatic rapid transit system, an environmentally friendly bus system and a modern tram for consultation. However, it has not yet decided and it is unknown when it will be completed to provide the connection.

▼Hung Hung Shui Bridge/Xia Village New Development Area has been selected as an environmentally friendly public transport mode▼

+16

+16

+16

The Government invites the MTR to Hung Hung Kiu Station and the South Island Line West Section Plan for the Southern District Council: I look forward to it

The Legislative Council Committee on Development supports the Hung Shui Kiu development project to be submitted to the Public Works Sub-committee for deliberation

The government applies for an allocation of 2.2 billion yuan to begin next year, and the preliminary works of the Hung Shui Bridge New Development Zone are expected to be occupied in 2024.

The government consults the public for two months on the three plans for environmental transportation research in the Hung Shui Bridge New Development Zone

01News

Hung Shui Kiu MTR Tuen Ma Line

Source: hk1

All news articles on 2021-05-29

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.