With the first planning of the surrounding area and the development of traffic, the construction of the future grammar school begins in the community of Aschheim, which will form the school campus together with the secondary school. The way to school should be as safe as possible.


With the first planning of the surrounding area and the development of traffic, the construction of the future grammar school begins in the community of Aschheim, which will form the school campus together with the secondary school.

The way to school should be as safe as possible.

Aschheim

- After the preliminary consultation in the building committee, the basic road planning was decided unanimously.

The most important decision is to choose a one-way street past the future grammar school when Ludwig-Thoma-Straße is extended for development.

With this measure, the municipality wants to prevent through traffic of any kind right from the start.

Pedestrian and bike paths are separated

To the east and west of the road, footpaths and cycle paths are separated from each other in order to minimize dangerous situations.

A pick-up and delivery lane is planned on the 350-meter-long road with an area of ​​around 6,000 square meters.

Here, on the one hand, the buses can stop and, on the other hand, parents who, for example, let injured or otherwise handicapped students get off.

Mayor Thomas Glashauser (CSU) emphasized that the teaching swimming pool on the school campus will create more school bus traffic than just before and after class.

Additional curve - because the municipality does not have all the properties

There will be a turn around in the middle of the street.

This has to be because the municipality does not own all the land.

Despite the one extra curve, the community sees a good situation because the access road can be realized with sufficient ground and the ways to school can be controlled generously.

It was suggested that the municipality of Ismaning, for example, has to organize traffic to its grammar school with an existing residential street in a residential area.

New road will cost around 1.15 million euros

The cost of the new street, including lighting and greenery, is around 1.15 million euros according to the cost estimate.

They will be included in the package for the development costs of the school campus and included in the 2022 budget.

Preparatory earthworks are much cheaper

The municipal council has already awarded a first order. For 171,000 euros, the Aschheim-based company ADS Gala-Bau Spiegl was the cheapest bidder for the preparatory earthworks for the archaeological removal. This award was gratifying, because originally the cost of this item had been calculated at 484,000 euros. NICO BAUER

Source: merkur

All news articles on 2021-06-28

You may like

News/Politics 2024-03-06T11:17:42.959Z
News/Politics 2024-03-12T15:22:46.364Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.