The government's application for rezoning of the Tseung Kwan O Underground Car Park with a total of 395 parking spaces on two floors is expected to be completed in 2026

2021-08-13T04:27:00.221Z


The government plans to build town parks in areas 66 and 68 in Tseung Kwan O. Among them, in Area 66, which is next to the private residential "Tianjin", the authorities earlier proposed the construction of an underground car park, but the high cost aroused opposition. Transport Department


The government plans to build town parks in areas 66 and 68 in Tseung Kwan O. Among them, in Area 66, which is next to the private residential "Tianjin", the authorities earlier proposed the construction of an underground car park, but the high cost aroused opposition.


The Transport Department recently submitted an application to the Town Planning Board for the construction of an underground car park. It plans to develop a two-story underground car park under the town park, which can provide a total of 395 parking spaces.

The project is expected to be completed in 2026.


The government had planned to build town parks in areas 66 and 68 of Tseung Kwan O earlier, among which an underground parking lot would be built in area 66.

The Transport Department has applied to the Town Planning Board for the construction of a two-story underground car park underneath the town park in Area 66 of Tseung Kwan O, that is, the middle part of the second and third phases of the private residential "The Wings", which can provide a total of 395 Parking spaces, including 300 parking spaces for private cars, 30 parking spaces for motorcycles, etc.

The project is expected to start in 2023, and the temporary parking lot with 788 parking spaces will be suspended by then.

According to the authorities, in response to parking needs, it will study the provision of additional parking spaces in other locations in the district.

Since 2017, the authorities have proposed to build town parks in areas 66 and 68 of Tseung Kwan O. Among them, a town park and an underground parking lot are proposed to be built on the site of area 66.

However, at that time, residents in the district aroused objections, questioning the high cost of construction, and the average cost of each parking space was millions of dollars. They were also worried that the completion date of the town parks would be delayed.

The redevelopment of the Yuen Long Tung Tau Industrial Zone Stadium plans to build an additional underground car park with 190 parking spaces. The Sham Shui Po Smart Car Park is expected to be completed in 2026. It will take 8 years to complete the study and completion. District Councillors will approve it too late. Construction of an automatic parking system on seven sites. Demolition of the "Chuanlong" car park in Yau Ma Tei. Chen Fan: Maintaining the opening of Gascoigne Road flyover is difficult

01News

Source: hk1

All news articles on 2021-08-13

You may like

News/Politics 2024-02-29T10:05:54.657Z
News/Politics 2024-04-05T10:15:22.741Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.