The work for the construction of the interim central bus station continues.
From September 2nd, there will be traffic disruptions.
Regensburg - The construction work on the provisional bus station is progressing.
According to the Regensburg City Administration *, the sidewalks are currently being rebuilt, as
reported by
idowa.de
.
The asphalting in Maximilianstrasse and Albertstrasse will then be carried out in September.
"The construction work is still very well on schedule, so that the interim central bus station can go into operation as planned," the city administration said confidently.
Regensburg: Traffic disruption due to construction work
Because of the construction work, there will be traffic disruptions from Thursday (September 2nd).
The Regensburger Verkehrsverbund (RVV) has already announced this.
Accordingly, Maximilianstrasse, from Albertstrasse to Ernst-Reuter-Platz, and on Albertstrasse, will be completely closed until Wednesday (September 8th).
Ernst-Reuter-Platz is also not accessible during this time.
In addition, there is no substitute stop at Ernst-Reuter-Platz.
The redesign of the interim central bus station started in March.
The total costs amount to around five million euros.
The bus station is scheduled to start operating in December.