New level crossing in Hausham: major construction site is finished earlier than planned

2021-09-14T17:05:51.177Z


The major construction site in Hausham will be finished earlier than planned. All closures are to be lifted by the end of October and traffic is to pass over the new level crossing.


The major construction site in Hausham will be finished earlier than planned.

All closures are to be lifted by the end of October and traffic is to pass over the new level crossing.

Hausham

- You could almost speak of partial retirement.

With the completion of Industriestrasse in Hausham, things will now be much quieter for the old level crossing as well.

The through traffic has been rolling past him again since Monday.

Only drivers who are heading for or coming out of Naturfreundestraße still have to cross the barrier system.

Since the construction work and thus the closure have now shifted back to Schlierseer Straße, the frequency is likely to decrease somewhat here as well.

Construction work is moving back to Schlierseer Straße

As construction manager Ferdinand Klettner from the engineering office Infra told our newspaper, the section from the adult education center to the parking lot at the train station is now being tackled.

The Schlierseer Straße will be excavated in this area in order to renew the drainage and bring in anti-freeze gravel.

The asphalting should take place in the 42nd or 43rd calendar week.

The overall project for relocating the Hausham level crossing was completed by the end of October - one month earlier than planned.

After decades of waiting for the construction site, it has now been completed faster than expected.

Also read: B307 at the Westenhofen level crossing is fully passable again

According to Klettner, the acceptance of the new level crossing is still scheduled for the period from September 20 to 23.

Just in time for the completion of Schlierseer Straße at the end of October, the cars will then roll over the new barrier system for the first time.

There is already a foretaste of the new traffic routing - in the form of the already marked turning lanes on Industriestrasse.

The traffic lights are also set up.

The old Hausham level crossing will soon be able to retire for good.

so-called

Source: merkur

All news articles on 2021-09-14

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.