Sand Middle Line. Live | The cross-sea section of the East Rail will open to traffic from June to July next year, Luohu can reach Admiralty directly

2021-10-22T08:48:15.008Z


The Tuen Ma Line was opened to traffic in June this year. However, the cross-sea section of the East Rail Line, which is also part of the Sha-Central Line project, has been officially opened to traffic repeatedly. It is planned to start operation in 2019 when the original project was launched and will be extended to the first quarter of 2022 next year. Open to traffic.


The Tuen Ma Line was opened to traffic in June this year, but the cross-sea section of the East Rail Line, which is also part of the Sha-Central Line project, has been officially opened to traffic repeatedly. It is planned to start operation in 2019 when the original project was launched and will be extended to the first quarter of 2022 next year. Open to traffic.

However, the project has recently been affected by the progress of East Rail's conversion to 9-car trains and the introduction of new signal systems. It is still unknown whether the revised target can be crossed in the first quarter of next year.

"Hong Kong 01" received the latest news, stating that after the MTR has been catching up with the progress, the latest date for opening to traffic is the second quarter of next year.


The MTR stated that the project is progressing well after the recovery of the cross-harbour section of the East Rail. After discussing with the Hong Kong government, the cross-harbour section of the Sha-Central Line will be opened to traffic from June to July next year.

In the past, the MTR has always stated that it is trying its best to recover the progress of the project after the East Rail cross-sea section.

The MTR originally planned to suspend the section of East Rail Mong Kok East to Hung Hom Station on 10 of these Sundays from January to October this year for the East Rail cross-harbour rail connection project. It is now pending the MTR’s announcement. An engineering day.

As for other related works in the cross-harbour section, the MTR said earlier that most of the new rail connections, as well as the convention and exhibition and Admiralty station station projects have made some progress.

MTR will report the latest progress of the East Rail cross-sea section at 4:30 today (22nd), and the press conference will be broadcast live on "Hong Kong 01".


▼Opening of 9-card trains▼


+25

The Shazhong line project, with a total cost of nearly 91.5 billion yuan, is divided into sections from Tai Wai to Hung Hom and a section across the sea.

The Tai Wai-Hung Hom section has been opened to traffic along the Tuen Ma Line. It will be fully opened at the end of June this year. As for the project to connect to the East Rail Crossing the sea, the opening time has not been determined.

The MTR said earlier that in response to the East Rail cross-harbour rail connection project, it would be necessary to suspend the service from Mong Kok East Station to Hung Hom Station on 8 of these Sundays from January to October this year, and connect the existing East Rail track to The newly built platform of Hung Hom Station.

The MTR originally planned to replace the new signal system and the new 9-car train last year, but it was revealed by "Hong Kong 01" that the new signal system had "wrong route" causing the train to "wrong line" and other problems. In October last year, it stopped at the door. Switch to the new signal system, and only switch to it on February 6 this year.

With the launch of the new signal system, East Railway is arranging to mix 9-carriage trains with traditional 12-carriage trains. It did not mention the original goal of replacing all trains with 9-carriage trains within six months.

The 9-car trains even experienced problems one after another. During the typhoon hit Hong Kong this month, many trains failed, and the replacement of trains has not yet been completed.

As for the two stations on the cross-sea section of the East Rail, related works at the Convention and Exhibition Station and Admiralty Station are also progressing.

The MTR released a number of new photos of the expansion of Admiralty Station earlier, showing that the works have been roughly completed

▼On June 27th, the first special train on the Tunma line opened to traffic ▼


+5

▼On June 27th, the entire Tunma line was opened to traffic. Railway fans entered the gate first at Songhuangtai Station▼


+1

Sha-Central Line | MTR suspends service from Mong Kok East to Hung Hom Station on Sunday to install overhead cable Tuen Ma Line | Looking back at the series of scandals in the Sha-Central Line project, cutting walls and cutting ribs to cross the sea, the Sha-Central Line is still indefinitely | Leighton charged for violation The "Buildings Ordinance" case is postponed in July for another report on the Tunma Line | Tian Beichen: Shazhong Line is the fuse of the merger of the two railways to kick off the biggest regret in Causeway Bay North Shazhong Line | Hung Hom Station Investigation Committee made 78 recommendations to implement 50 audit teams: The progress is satisfactory in the Shazhong line. Exclusive | Leighton subsidiary has won the bid twice and changed its name. Multiple clones can be bid for the government exclusive. The sister company of Leighton, the protagonist of the Shazhong line scandal, won the 210 million government contract during the suspension of the Shazhong line. Station Seepage Water Highways Department: Does not affect the power and signal system Shazhong Line | East Rail Crossing has repeatedly postponed the expansion of Admiralty Station partially exposed netizens’ messages to turn old accounts on Shazhong Line | East Rail cross-sea section raw materials open to traffic in the first quarter of next year Previously more severe Shazhong line|Fax agency unveils Leighton Hung Hom station to buy more than 200,000 screw caps, involving 16 million

01News

Source: hk1

All news articles on 2021-10-22

You may like

Trends 24h

News/Politics 2024-03-28T06:04:53.137Z

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.