More patience is required in Wartenberg: The full closure of Strogenstraße at house numbers 12 to 17 must be extended by three weeks until December 18.
Wartenberg - This is announced by the district office.
The reasons are unforeseeable delays in the construction of the throttle structure for the drainage system and work in the street area.
As the head of the Wartenberg building authority, Marco Lachmann, informed our newspaper when asked, an unknown wastewater sewer was discovered in the construction site area.
“This had to be re-laid, including several house connections connected to it,” writes Lachmann.
In the meantime, nothing has changed about the diversion: It continues to take the ED 2 (Pesenlerner Straße) towards Berglern, the St 2331 (Erdinger Straße) towards Langengeisling and the St 2082 via Tittenkofen, Reichenkirchen and Fraunberg to Wartenberg.