Homs-Sana
The General Electricity Company of Homs Governorate has rehabilitated and maintained a number of transmission centers and repaired more than 18 faults in the countryside and the city during the past month.
Engineer Saleh Omran, director of the Homs Electricity Company, told SANA that the company’s workshops rehabilitated the southern Tire Maaleh 630 transmission center and replaced a damaged 100 kVA transformer in the western Farhaniya village, and another damaged one in the Wadi al-Dahab neighborhood with a capacity of 360 kVA.
Omran added that the capacity of a pre-fabricated transformer center in the Abbasiya neighborhood was improved from 360 to 1000 kVA, in addition to raising the capacity of transformers in Jdeidet, Qatina, al-Raqama and Palmyra Square.
Lara Ahmed
Follow Sana's news on Telegram https://t.me/SyrianArabNewsAgency