Tölzer Isarbrücke completely closed from Friday afternoon Created: 01/27/2022, 19:00 By: Veronika Ahn-Tauchnitz For days, signs throughout the city have been pointing out the bridge closure and the detour route. © arp Road users should be prepared for some traffic obstructions in and around Bad Tölz from this Friday afternoon (January 28th). The reason: the Isar bridge on the bypass will be cl


Tölzer Isarbrücke completely closed from Friday afternoon

Created: 01/27/2022, 19:00

By: Veronika Ahn-Tauchnitz

For days, signs throughout the city have been pointing out the bridge closure and the detour route.

© arp

Road users should be prepared for some traffic obstructions in and around Bad Tölz from this Friday afternoon (January 28th).

The reason: the Isar bridge on the bypass will be closed from 2 p.m. to around 6 a.m. on Monday morning.

Bad Tölz – The closure of the Tölzer Isar Bridge from this Friday afternoon (January 28) to Monday morning applies to all motor vehicle traffic.

Only pedestrians and cyclists can use the temporary footpath and cycle path.

Diversion takes place in town via Bockschützstraße

The diversion for both directions of travel takes place within the city via Bockschützstraße, the municipal bridge over the Isar, the Kapellengaststeig to connect Lenggrieser Straße to the federal highway 13 south of the Moraltpark.

The detour route is signposted.

The bridge has been under construction for months

The bridge has been under construction for months.

According to the Weilheim State Building Authority, four new crossbeams will be concreted this weekend on the underside of the bridge between the two longitudinal beams.

This lasts until around 8 p.m. on Friday.

Depending on time and temperature, the strength of the concrete increases until Monday night to such an extent that traffic can roll over the bridge again at 6 a.m. on January 31.

Even a truck could cause irreparable damage

For structural reasons, however, traffic weighing more than 3.5 tons may not be driven on the bridge while the concrete is hardening.

"Since the diversion of traffic over 3.5 tons cannot be guaranteed with 100 percent certainty from a traffic point of view and even a 40-ton truck on the bridge would cause irreparable damage to the crossbeams, the Weilheim State Building Authority decided to to completely close the bridge during this time," says a press release.

On average, around 16,000 vehicles roll over the bridge every day

The almost 133 meter long Isar bridge of the B 472 was built in 1981.

On average, around 16,000 vehicles use the B 472 every day. (tk)

Bad-Tölz-Newsletter: Everything from your region!

Our Bad Tölz newsletter regularly informs you about all the important stories from the Bad Tölz region - including all the news about the Corona crisis in your community.

Sign up here.

Source: merkur

All news articles on 2022-01-27

You may like

Trends 24h

News/Politics 2024-04-18T09:29:37.790Z
News/Politics 2024-04-18T11:17:37.535Z

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.