The Limited Times

Now you can see non-English news...

Freising: Redesign in the city center is making progress - Moosach has been partially opened

2022-05-13T07:37:10.073Z


Freising: Redesign in the city center is making progress - Moosach has been partially opened Created: 05/13/2022, 09:25 am By: Lena Hepting Large parts of the Moosach are already open. © Felix Matthey The construction work on Obere Hauptstrasse is progressing. The Moosach is already open and there are also suitable seating options. The construction work on Obere Hauptstraße is making good pro


Freising: Redesign in the city center is making progress - Moosach has been partially opened

Created: 05/13/2022, 09:25 am

By: Lena Hepting

Large parts of the Moosach are already open.

© Felix Matthey

The construction work on Obere Hauptstrasse is progressing.

The Moosach is already open and there are also suitable seating options.

The

construction work on Obere Hauptstraße

is making

good progress

, as Michael Schulze, coordinator of the inner city conversion in the Office for Urban Planning and Environment, explains: While the engineering structure of the Moosach is currently still open at the junction with Bahnhofstraße and various lines are being laid, at the back Paving work prepared in the area at the level of Kochbäckergasse.

Moosach opening in the city center: Seating is already available

Citizens already have the opportunity (which they gladly use) to linger on the steps along the

open Moosach

and thus get a first impression of the redesigned Upper Old Town.

The engineering structure has been completed up to the junction with Bahnhofstrasse, where the Moosach is already flowing through its new riverbed.

The paving work around Stieglbräugasse has already been completed and will start soon here on Kochbäckergasse.

© City of Freising

The excavation pit on Bahnhofstrasse allows an unobstructed view of the large residual water pipes through which the Moosach water is currently still being routed.

Tried and tested bored piles are located along these pipes, which will in future carry the outer walls of the Moosach.

Power, district heating and telecommunications lines are currently being laid under the foundation through so-called culverts.

Completion of the engineering structure in this area is scheduled for mid-July.


Moosach opening in the city center: Paving work is partially completed

In the direction of the Karlwirt crossing, the redesign of the Obere Hauptstraße continues to take shape.

The stairs along the Moosach already invite you to linger, and the paving work has already been completed at Jägerwirtsgasse and Stieglbräugasse.

The locations for several trees and shrubs were also created here, which should ensure a better city climate in the future.

The paving work between Stieglbräugasse and Kochbäckergasse is currently being prepared.

Source: merkur

All news articles on 2022-05-13

You may like

News/Politics 2024-02-28T07:15:38.118Z
News/Politics 2024-03-14T18:05:29.744Z
News/Politics 2024-04-05T06:07:52.632Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.