95 new apartments: construction work on Egerlandstrasse on schedule

2022-05-24T04:17:54.329Z


95 new apartments: construction work on Egerlandstrasse on schedule Created: 05/24/2022, 06:00 By: Doris Schmid This is where the new city center is being built: new residential and commercial buildings are being built on Egerlandstrasse. © Hans Lippert The Geretsried building cooperative's largest project to date is on schedule. 18 preliminary contracts for a total of 95 apartments have alrea


95 new apartments: construction work on Egerlandstrasse on schedule

Created: 05/24/2022, 06:00

By: Doris Schmid

This is where the new city center is being built: new residential and commercial buildings are being built on Egerlandstrasse.

© Hans Lippert

The Geretsried building cooperative's largest project to date is on schedule.

18 preliminary contracts for a total of 95 apartments have already been concluded.

Geretsried – The plaster is being applied to the facade and the interior work is underway.

The new building of the building cooperative Geretsried (BG) on Egerlandstraße, the BGZ2, should be finished in autumn.

Can this date be kept in view of announced material bottlenecks due to the Ukraine war?

"Before November 1st, nothing will work," says BG Managing Director Wolfgang Selig.

But he is confident that commercial and private tenants will be able to move in later this year.

The large commercial units on the ground floor have already been let to the discounter Aldi and the drugstore chain Rossmann.

As reported, the building cooperative recently started renting out a total of 95 apartments.

According to Selig, 18 preliminary contracts have been concluded so far.

The price per square meter for the privately financed apartments is between 13 and 14 euros.

No delays worth mentioning: “We just had a dizzy spell”

According to Selig, there have been no significant delays since November 2019, when demolition of the old building began.

But it could have turned out very differently.

"We were just dumb," says the BG managing director, referring to the size of the construction site and the selected building design.

Last year it was "brutally difficult" to get lumber.

"But after the city council decided on a flat roof for this property, we didn't have a wooden roof truss from a carpenter," explains Selig.

Consequently, the lack of timber did not affect the construction site on Egerlandstraße.

"There's a concrete cover on it, and it's extensively greened."

Wolfgang Selig Managing Director of the Geretsried building cooperative.

©sh

BG was similarly lucky with the insulation.

The decision was made to use mineral wool because "styrofoam is not undisputed in terms of disposal and fire protection".

Although this type of insulation costs more, it is even more reliable when it comes to fire protection.

In addition to timber, styrofoam was also difficult to obtain in 2021.

Due to a fire in a large American company, the Americans bought this insulating material on a large scale in Europe.

"Since we hadn't planned any styrofoam insulation, we didn't get these delivery problems either," says Selig, relieved.

But it was all a happy coincidence and not due to the foresight of the client.

"When in doubt, missing a single piece can affect the whole opening"

Selig hopes that the construction schedule can continue to be met.

But he admits that forecasting is difficult.

"We don't know for sure whether we'll get balcony and stairwell railings in time." Such metals - sheet metal and angles, for example - would mostly come from Eastern Europe.

"We are careful with information," says the managing director.

"When in doubt, missing a single piece can spoil the whole opening."

also read

Brutal attack on party guests: the police provide information on the alleged "main perpetrators"

Why Abdul Barakat loves working as an electrical engineer

But Selig remains optimistic - also with regard to the road construction, which is in the hands of the city.

"At the moment it looks pretty good that the city and we will finish at a similar time." He hopes that the scaffolding on BGZ2 can be dismantled by July at the latest, "then the city can start asphalting the base layer".

By the way: everything from the region is also available in our regular Wolfratshausen-Geretsried newsletter.

Source: merkur

All news articles on 2022-05-24

You may like

News/Politics 2024-03-18T06:16:09.392Z
News/Politics 2024-02-29T17:04:16.637Z

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.