Price explosion hits second fire station

2022-05-27T08:18:25.151Z


Price explosion hits second fire station Created: 05/27/2022, 10:11 am The existing Brucker fire station is a little off the beaten track in the north-west of the city. © Archive The second fire station on Flurstrasse in Fürstenfeldbruck is becoming more expensive: the costs are now 7.3 million euros. Another problem: The construction companies are trying to pass on the explosion in material pr


Price explosion hits second fire station

Created: 05/27/2022, 10:11 am

The existing Brucker fire station is a little off the beaten track in the north-west of the city.

© Archive

The second fire station on Flurstrasse in Fürstenfeldbruck is becoming more expensive: the costs are now 7.3 million euros.

Another problem: The construction companies are trying to pass on the explosion in material prices.

Fürstenfeldbruck – The total costs for the new fire station II with apartments on Flurstrasse will increase by a further 373,000 euros (5.4 percent).

This means that the original construction costs have risen from a total of 6.9 million euros to 7.3 million euros.

The wood price

The reason for the additional costs can be attributed to various causes, the architect reported to the planning and construction committee last Wednesday evening.

The work for the locksmith had to be tendered twice.

The costs for the façade rose, as did those for the site power supply and site heating.

The ancillary costs also incurred slightly higher costs due to additional experts and rescheduling.

But you have to fight especially with the massive construction price increases, it said.

Wood, for example, now costs up to 30 percent more.

The difference was mainly at the expense of the companies.

However, they in turn tried to pass on the additional costs they have to bear via supplements.

(By the way: everything from the region is now also available in our regular FFB newsletter.)

Due to the corona pandemic, the appointments got through relatively well, the architect continued.

Sometimes you had to get over a one or two week absence when employees of companies were sick.

The delivery difficulties for wood and various other raw materials were more serious.

There are currently severe delivery bottlenecks due to the Ukraine war for certain components, such as steel.

Working together with the companies turned out to be difficult overall.

still keep the appointment

60 percent of the budget has already been settled with the companies, 40 percent is still open.

In any case, the companies must check the plausibility of any cost increases that the client has incurred as a result of the war in Ukraine.

But some savings were also achieved, for example by reducing the number of wall tiles or painting the exposed concrete surfaces.

There were also some household leftovers that could be transferred.

also read

Parents sound the alarm: Give the schoolchildren back the gym - and look for other alternatives for refugees

A wind turbine could be built here - the system would be higher than the existing ones

The total costs of the new building are broken down into 40 percent for the housing area and 60 percent for the fire brigade area.

The architect concludes that one is in good spirits that the move-in date of August 1st can be kept.

You can find more current news from the district of Fürstenfeldbruck at Merkur.de/Fürstenfeldbruck.

Source: merkur

All news articles on 2022-05-27

You may like

Trends 24h

News/Politics 2024-04-17T18:08:17.125Z

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.