Blocked for four weeks: Municipal utilities dig up Oskar-von-Miller-Platz

2022-08-01T16:41:32.494Z


Blocked for four weeks: Municipal utilities dig up Oskar-von-Miller-Platz Created: 01/08/2022, 18:30 By: Andreas Höger An important hub is at a standstill: Yesterday, the preparatory work for the large construction site of the municipal utilities began at Oskar-von-Miller-Platz. The intersection is completely closed until August 28th. © Thomas Plettenberg An important traffic hub in Holzkirche


Blocked for four weeks: Municipal utilities dig up Oskar-von-Miller-Platz

Created: 01/08/2022, 18:30

By: Andreas Höger

An important hub is at a standstill: Yesterday, the preparatory work for the large construction site of the municipal utilities began at Oskar-von-Miller-Platz.

The intersection is completely closed until August 28th.

© Thomas Plettenberg

An important traffic hub in Holzkirchen has been standing still since Monday morning (1 August).

The Oskar-von-Miller-Platz is closed for four weeks due to a construction site by the municipal works.

Holzkirchen

– Since Monday (August 1st) anyone who wants to drive through Holzkirchen will very quickly find themselves in front of site fences and excavators: Oskar-von-Miller-Platz, a central hub in and out of Föching and Otterfing, is complete for four weeks closed because the Holzkirchen municipal works lay a power line across the square.

The cable is routed from Baumgartenstrasse in the direction of Rosenheimer Strasse in order to connect the new buildings that have been built there (next to the cemetery).

Traffic will be diverted over a large area via the Nordspange (MB 9), the corresponding routes are signposted.

Originally, the district office had also pointed out alternative routes through the town, but these inner-town bypasses are now not signposted.

Pedestrians and cyclists can pass through the construction site, according to the municipal works.

As its managing director Albert Götz announced, depending on the progress of construction, partial connections should also be released for car traffic;

Steel plates then bridge the trench.

According to Götz, however, this will be decided at short notice and only be possible temporarily.

In principle, however, motorists must assume a full closure and, according to Götz, should refrain from risking the through road on the off chance.

The closure is necessary because a power line that previously came from Baumgartenstrasse and turned towards Münchner Strasse had to be drawn across the square.

According to Götz, it is a main line (20,000 volts medium voltage).

In particular, the new buildings that have recently been built between Rosenheimer Strasse and the cemetery are being developed.

The municipal utilities set up a new transformer house there, which is now to be threaded into the main ring line.

The construction site runs almost the whole month.

Traffic on Oskar-von-Miller-Platz should be flowing again by Sunday, August 28 at the latest.

More information on the subject can be found here.

Source: merkur

All news articles on 2022-08-01

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.