Work on the bridge: only on one track over the Sylvensteinsee Created: 08/13/2022, 16:00 By: Andreas Steppan Work on the bridge pillars: Due to renovation work, the Sylvenstein Bridge will probably only be passable in one lane until the end of October. A traffic light regulates the traffic. © Arndt Pröhl Work is currently underway on the Sylvenstein Bridge. A total of around 1.3 million euros


Work on the bridge: only on one track over the Sylvensteinsee

Created: 08/13/2022, 16:00

By: Andreas Steppan

Work on the bridge pillars: Due to renovation work, the Sylvenstein Bridge will probably only be passable in one lane until the end of October.

A traffic light regulates the traffic.

© Arndt Pröhl

Work is currently underway on the Sylvenstein Bridge.

A total of around 1.3 million euros will go into the repairs.

Lenggries – If you want to drive over the Sylvenstein Bridge by car, you may have to be patient at the moment: As was the case last year, the road is closed on one side and a traffic light controls the traffic.

The reason for this is repair work on the bridge pillars and the underside of the bridge, as the responsible site manager Karin Bader from the Weilheim State Building Authority explains.

Water damage to the bridge piers will be repaired

The bridge was already being worked on in 2021. "We renewed the transverse joints there," explains Karin Bader.

These are visible on the road as stripes about 60 centimeters wide.

The reason was that these joints between the individual elements were leaking, so that water dripped onto the concrete pillars underneath and caused damage there.

By the way: Everything from the region is now also available in our regular Bad Tölz newsletter.

Such damage - such as concrete spalling or cracks - will now be repaired this year, says Bader.

Construction work began after the G7 summit at the end of June.

If everything goes according to plan, everything should be ready by the end of October.

However, it is difficult to predict precisely at this time.

"We are also affected by delivery bottlenecks," says the site manager.

A traffic light will direct traffic past the construction site

The traffic light, which alternately directs traffic from both directions in one lane past the construction site, is traffic-controlled, so that the direction of travel from which more vehicles are coming is always green longer.

The cost of the renovation is estimated at 1.3 million euros.  

You can find more current news from the region around Bad Tölz at Merkur.de/Bad Tölz.

Source: merkur

All news articles on 2022-08-13

You may like

News/Politics 2024-03-01T08:14:29.221Z

Trends 24h

News/Politics 2024-03-27T16:45:54.081Z

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.