The first house on the Hintersberg is up - canal construction up to the Wackersbergerhöhe poses a challenge
Created: 10/23/2022, 5:00 p.m
Still alone in the field: The first semi-detached house in the new urban building area Hintersberg 2 is finished.
©CS
The first semi-detached house is in the new urban development area on Hintersberg.
But the canal construction up to the Kogel poses a challenge.
The city is now examining a possible alternative.
Bad Tölz – The first semi-detached house on Hintersberg has been completed, reported Christian Fürstberger, head of the building authority, at the most recent meeting of the Tölz building committee.
In connection with the development of the new municipal building area, where the city of Bad Tölz has already sold 14 parcels for five semi-detached houses and a four-in-hand vehicle in addition to planned leasehold properties.
Am Hintersberg: Slightly behind schedule - Other landowners can start building soon
You are slightly behind schedule.
House connections, divisions and broadband have been relocated.
The base course of the access road is to be installed in November.
"Then the other landowners can also start building."
You can find more current news from the region around Bad Tölz at Merkur.de/Bad Tölz.
Canal construction up to the Kogel poses a challenge: the bypass road
Fürstberger's statements regarding the canal construction for the new hotel construction on the Wackersbergerhöhe were interesting.
Around 700,000 euros have been earmarked for this so far.
This canal construction up to the Kogel poses a technical challenge at one point: the bypass road.
So far it was planned to attach the canal to the existing bridge, but according to Fürstberger this would be "very complicated".
In order to reduce costs, they have now considered "pushing through" under the main road.
Unfortunately, it turned out that the subsoil was much worse than expected.
Now check whether you can insert a steel tube.
Fürstberger spoke of a sixth amount that could be saved.
The last possibility is the connection to the bridge, for which a contractual construct with the Weilheim State Building Authority would also be necessary.
Ground conditions have changed due to the construction of the bypass
Josef Steigenberger (CSU) was surprised that apparently there was no soil report.
"That dates back to the 1970s," replied Fürstberger.
In addition, the construction company was quite sure that the cheaper way of pressing through would work.
In addition, according to Mayor Ingo Mehner, the ground conditions had changed due to the construction of the bypass.
also read
Thieves spy on kiosk in Tölz - and fail because of attentive operators
Accident on Maustraße Vorderriß-Wallgau: Missing driver triggers search
Dredging up the federal road and laying a canal in it - possibly a possibility
Martin Harrer (FWG) asked whether one could simply dredge up the main road above ground and lay the canal in it.
Otherwise there are enough construction sites on the B 472.
"We'll have to look into that," Fürstberger replied.
Johannes Gundermann (Greens) finally checked whether there could be penalties because the canal is not finished.
"No," Fürstberger replied with conviction, "we can do it."
By Christoph Schnitzer