The Tseung Lam Tunnel and the Tseung Kwan O Cross Bay Link Road are less than a month away from opening to traffic. Today (20th) the Community Chest Walk for Millions was also held at the Tseung Kwan O Cross Bay Bridge. However, what the reporter saw on the bridge today, there are still three major problems


The Tseung Lam Tunnel and the Tseung Kwan O Cross Bay Link Road are less than a month away from opening to traffic. Today (20th) the Community Chest Walk for Millions was also held at the Tseung Kwan O Cross Bay Bridge.

However, what the reporter saw on the bridge today, there are still three major problems that have not been resolved, including the double-arch steel bridge described by the authorities as a "butterfly" and symbolizing "infinity", which is suspected to have rust stains; some parts of the bridge are exposed steel bars; spotlights and wires are messy. It's in a mess and hasn't been cleaned up.

"Hong Kong 01" is making inquiries with the Civil Engineering and Development Department.


Fang Guoshan, a member of the Sai Kung District Councilor who is qualified as an engineer, said that rust stains were found during previous inspections. The Civil Engineering and Development Department explained that during the transportation of the steel bridge, it was necessary to clamp it with instruments, so the stains appeared.

Fang criticized that the authorities should step up cleaning, or paint to solve the stains, and pointed out that the exposed steel bars may cause danger.


The lights and wires of the Cross Bay Bridge in Tseung Kwan O were exposed, causing chaos and twisting.

(Photo by Huang Weilun)

The Tseung Kwan O Cross-Bay Link is about 1.8 kilometers long, including a 1-kilometer offshore double-arch steel bridge. It is the first marine viaduct in Hong Kong that combines traffic lanes, cycle paths and pedestrian paths. Its approved budget is 5.6 billion yuan.

The Community Chest Walk for Millions was held today at Link Road. Participants can first step on the Cross Bay Bridge, including its driving path, before the official opening to traffic. The reporter also attended to observe.

According to the CEDD's documents, the Cross Bay Bridge is assembled and assembled. Mainland factories manufacture a large number of prefabricated components, and then transport the prefabricated components to Hong Kong through large-scale transportation and hoisting construction machinery, and then assemble them at the construction site.

Among them, the double-arch steel bridge is likened to a butterfly flying on the sea.

Many brown stains were found on the "butterfly wings" of the Cross Bay Bridge in Tseung Kwan O, resembling rust stains.

(Photo by Zhang Haowei)

However, the reporter approached the "Butterfly Wings" today, but found brown stains in many places, like rust stains; there were also traces of collisions on the iron bars.

In addition, when walking on the carriageway, it was also found that steel bars were exposed through the concrete.

After stepping on the pedestrian section, when observing the spotlights of the bridge, I also found that many wires were exposed and not stored, and it was very confusing.

Fang Guoshan also participated in the Walk for Millions with her neighbors this morning. She said she was excited and many people praised her, but the above situation cannot be ignored.

She continued that rust stains were found during the previous inspection. The CEDD explained that the steel bridge needs to be clamped and fixed with instruments for a long time during transportation, so stains appeared.

However, she believes that the bridge cost billions of dollars, and it is not ideal to have rust stains before it is opened. It will affect the appearance and should be cleaned or even painted before it is opened to traffic.

Fang Guoshan: It's really a rush, so exaggerated

In addition, the Jianglan Tunnel, which was opened simultaneously with the bridge, had an outbreak of epidemics and was finally postponed.

After Fang Guoshan saw the photos of exposed steel bars, she felt that it would be dangerous in the event of an accident, and bluntly said: "It's really a rush, so exaggerated", the situation is unreasonable.

Ni Xueren, a senior civil engineer, also said that the situation "must not be normal", but it is difficult to estimate the reason.

He explained that it is possible that the work has not yet been completed, but he believes that there are no structural issues involved, but the situation may not be ideal.

He also compared that the situation is like a renovation project, sometimes people will move in before the completion of the project, but "it's uncomfortable and not ideal".

As for the issue of exposed wires, Fang Guoshan said that although there are railings separating pedestrians from spotlights and electric shooting, I am worried that someone will vandalize it or touch it with "multiple hands"; and if it is exposed, there will be maintenance problems.

She suggested that, in addition to properly storing the wires, plastic boards should also be placed between the railings and the sidewalk.

Ni Xueren estimated that the current wires are signal wires used to test some instruments, but he emphasized that they should not be exposed.

A Million Journey|Participants take the lead in stepping on the Tseung Kwan O Cross Bay Bridge and praised the special experience and wonderful scenery Those with yellow codes are 6 kilometers away from the sea, facing the sea breeze, Tseung Kwan O Cross-Bay Bridge, and 8 great places in the Sunday Million Walk Pioneering Area: Not only the red leaves, cycling

Source: hk1

All news articles on 2022-11-20

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.