Earthworks at City Hall will not be finished by the end of the year

2022-12-17T07:36:21.937Z


Earthworks at City Hall will not be finished by the end of the year Created: 12/17/2022, 8:30 am By: Harald Hettich The earthworks in Neubiberg come to a halt. © hh Unpleasant facts about the new town hall in Neubiberg. There is a problem with the earthworks. The company commissioned has not yet completed the work scheduled for the end of the year. Neubiberg - An increase in costs due to nece


Earthworks at City Hall will not be finished by the end of the year

Created: 12/17/2022, 8:30 am

By: Harald Hettich

The earthworks in Neubiberg come to a halt.

© hh

Unpleasant facts about the new town hall in Neubiberg.

There is a problem with the earthworks.

The company commissioned has not yet completed the work scheduled for the end of the year.

Neubiberg

- An increase in costs due to necessary adjustments to conditions of a good 440,000 euros to a currently forecast total investment sum of 22.1 million euros: Compared to the often hour-long skirmishes in the planning of Neubiberg's flagship project for a new building and a renovation of the town hall complex, the current one went well Status report by the project controller Ferdinand Weiß in the municipal council was still comparatively harmonious.

New deadline for completion

In doing so, Ferdinand Weiß again had to address unpleasant facts in a factual presentation.

Since the building permit was granted at the end of June, work has been going on at Rathausplatz, dismantling and demolishing.

Façade elements are replaced or renewed, trees are felled and scaffolding is erected.

But there is still a problem with the earthworks.

The company commissioned has not yet completed the work scheduled for the end of the year and the construction of the shoring.

"We put the company in default," said Weiß.

This takes the form of a letter of default in which the client requests the contractor to complete the agreed construction work within a newly set deadline.

Start of shell construction at the beginning of the year

The shell construction is scheduled to begin at the beginning of the new year, and timber construction for the hybrid building from the summer.

After all, they want to celebrate completion at the end of 2024.

In return, one accepts further additional costs that have arisen during the implementation planning.

The biggest expense is the repair and replacement of the roof for at least a quarter of a million euros.

Structural improvements (74,000 euros), sealing the basement walls (61,000 euros), planning and implementing further IT connections, including cooling the components (almost 50,000 euros).

Almost half of the trades awarded

According to Weiss, the journey is apparently going in the right direction.

"Despite the difficult conditions, we have already awarded 44 percent and thus almost half of all trades," emphasizes the expert.

The commissioning of heating, ventilation and plumbing is currently in full swing.

Main building project

"Our most important building construction project is in full swing," emphasized Mayor Thomas Pardeller (CSU).

The second mayor, Kilian Körner (Greens), remained critical of the numbers.

"What are the costs?" he wanted to know.

White stayed calm.

"Even with the current adjustments, we are still within the cost forecast," he emphasized.

Source: merkur

All news articles on 2022-12-17

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.