Al-Hasakah - SANA
The workshops of the General Electricity Company of Al-Hasakah completed the maintenance of the electric line linking the Al-Mabasta and Al-Ghazal substations, and electricity was restored to the people and service departments in the city of Al-Hasakah.
The Director General of the Electricity Company, Eng. Anwar Akla, stated in a statement to SANA reporter that the 66 kV line went out of service as a result of an unknown person throwing a cable on it, which led to a contact in the network, as the workshops carried out maintenance and restored service to the subscribers, indicating that the workshops carried out Also maintenance of 20 km lines.
In the areas of Amouda and Tartab.
In another context, the Qamishli Electricity Department, according to the plan, carried out maintenance networks and transmission centers for each of the centers (Grain Garage, Gas Garden, Abu Hussam, Saleh Abdi, Ghassan Garden, Northern Water Project, Abu Farid, Karama, Daham Park Center, Sahara Center, Teachers’ Residence Extension and Peace Center) and returned them to service.
It is noteworthy that the Swedish electricity generation facility stopped working yesterday, and the electric generation turbines were stopped for a period of three days to carry out maintenance in it.
Follow SANA's news on Telegram https://t.me/SyrianArabNewsAgency