“A year of processing and planning”: Benediktbeuern community busy with reconstruction after hail storm

2024-02-12T16:15:51.217Z

Highlights: “A year of processing and planning’: Benediktbeuern community busy with reconstruction after hail storm. There are also plans for a large construction project this year, which leaves little scope for further projects. The majority of the renovation work on the municipal buildings is scheduled to take place this year. But some things wouldn't be finished until 2025. Two bus stops in the direction of Kochel are to be converted to be barrier-free. The community is considering whether the village street could be repaired before the actual village renewal.



As of: February 12, 2024, 5:03 p.m

By: Franziska Seliger

Comments

Press

Split

Repairing the hail damage to municipal buildings – such as the town hall – is one of the central tasks for the municipality this year.

© Franziska Seliger

Reconstruction is the central issue for the community of Benediktbeuern after the severe hailstorm last year.

There are also plans for a large construction project this year, which leaves little scope for further projects.

Benediktbeuern – According to Mayor Anton Ortlieb, there are 21 municipal buildings in the monastery village.

Without exception, all of them were damaged by the storm at the end of August 2023.

They would now be gradually repaired - a process that of course began last year.

But there is still a lot of repair work to be done on the buildings this year, which fortunately were all insured, says Ortlieb.

Hail damage must be repaired on the buildings in the municipality of Benediktbeuern

It's not just roofs that need to be renovated.

Damage to the plaster or caused by water penetration must also be repaired.

In an interview with our newspaper, the mayor mentioned the repair of the school building roof, which is largely due to be carried out during the summer holidays, as an example.

Among other things, the facade of the town hall needs to be renovated.

The old pharmacy was also badly affected by the storm.

The mayor is certain that all of these measures together “will tie up our capacities.”

Anton Ortlieb, Mayor of Benediktbeuern.

© Ralf Gerard

“We’ll see to it that we work through it.

But it inhibits the community.” Above all, the building authority’s “personnel capacities” are so stretched that there is hardly any scope left for other projects this year.

The majority of the renovation work on the municipal buildings is scheduled to take place this year.

But some things wouldn't be finished until 2025.

Ortlieb does not say what objects these are.

Two bus stops will be converted to be barrier-free

Despite this work, two bus stops in the direction of Kochel are to be converted to be barrier-free this year.

This year, the community would also like to push ahead with the planning for the new building project at the former house of the Don Bosco sisters on Bahnhofstrasse.

As reported, a new building is to be built here that will accommodate a kindergarten for nine groups.

According to an initial cost estimate, the community has to expect a “high single-digit million amount,” said Ortlieb.

He mentions a sum of around six million euros, but admits: “There is still room for improvement.”

(Our Bad Tölz newsletter regularly informs you about all important stories from your region. Sign up here.)

Cleaning up the hail damage and planning the new kindergarten building: These are the two big issues for the community this year.

“It’s a year of processing and planning,” is how the mayor puts it.

And what about the village renewal project?

According to Ortlieb, at least the planning here should be completed this year.

A traffic show is also still pending.

My news

  • Carnival parade 2025: Reichersbeurers are planning big things and have Bad Tölz in their sights

  • 2 hours ago

    Blind hail offering Pit from Bichl: This is how he feels today

  • Strange man sneaks through private gardens - residents alert the police

  • Carnival parade in Lenggries: Colorful, happy, silly and a bit evil

  • 2 hours ago

    Lisa Steinbacher from Reichersbeuern continues with the podcast “but there”: read “The ice was quickly broken”.

  • 54 mins ago

    Tölz live: Maxi Pongratz as a guest at “Lust”lesen

There is also reason to celebrate in Benediktbeuern

Whether the village renewal can be carried out in a timely manner seems questionable, says Ortlieb.

Actually, the first construction phase should have been started in 2025 “at best”.

It is now clear: “This will not be sustainable.” On the one hand, because of the consequences of the hailstorm.

On the other hand, because federal funding would no longer be paid out.

“The village renewal will come,” Ortlieb is certain.

The only question is when the Free State will provide funds for this.

The community is therefore considering whether the village street could be repaired “on a small scale” before the actual village renewal because of its many damaged areas.

But there is also reason to celebrate in Benediktbeuern.

Among other things, a new maypole will be erected.

In addition, according to Ortlieb, the municipal coat of arms is 65 years old this year.

However, there will be no celebration for this occasion.

The school's 50th birthday is being celebrated.

But more details are not yet clear.

(fn)

You can find more news in our brand new Merkur.de app, now in an improved design with more personalization functions.

Directly available for download, more information can be found here.

Are you an enthusiastic user of WhatsApp?

Merkur.de will now keep you up to date via a new Whatsapp channel.

Click here to go directly to the channel.

Source: merkur

All news articles on 2024-02-12

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.