The next delay is looming: procurement madness brings the school construction site to a standstill

2024-02-26T08:53:39.597Z

Highlights: The next delay is looming: procurement madness brings the school construction site to a standstill. The Olching high school has been evacuated and the container settlement has been used as an interim school. But the renovation of the old building cannot begin. Reason: allocation problems. In Puchheim, old gymnasiums were demolished and replaced with new ones. But right from the start, during the demolition work, pretty much everything went wrong. There were delays, which in turn caused problems. At the beginning of this development was a company that the district office accused of “poor performance,” as it is called in official jargon.



As of: February 26, 2024, 9:44 a.m

By: Thomas Steinhardt

Comments

Press

Split

The high school in Olching.

© Weber (archive)

The Puchheim hall debacle is not yet over, and the next construction site disaster is already on the horizon.

This time in Olching.

Olching – It is already clear that the renovation of the high school in Olching will be significantly delayed.

Because in the background there is a real procurement crime thriller.

The Olching high school has been evacuated and the container settlement has been used as an interim school.

But the renovation of the old building cannot begin.

Reason: allocation problems.

Everything went wrong

But how can this happen?

This is where the Puchheimer-Verdruss construction site and a company that worked there come into play.

In Puchheim, old gymnasiums were demolished and replaced with new ones.

But right from the start, during the demolition work, pretty much everything went wrong.

There were delays, which in turn caused problems.

At the beginning of this development was a company that the district office accused of “poor performance,” as it is called in official jargon.

A legal dispute is pending, and the district authority has already been accused of not having sufficiently controlled the Schlecht company.

The legal dispute continues.

The relationship

The connection with Olching?

It's quite simple: the company from the Puchheimer-Verdruss construction site took part in the awarding process for the work in Olching - and promptly submitted the cheapest offer.

According to the procurement regulations, the administration and the district council are bound to this most cost-effective offer, observers assert.

It should be clear: from the perspective of the administration and the district council, it would practically border on madness to hire a company with which you have had extremely bad experiences and with which you are in legal dispute.

The district's veto now rests with the contracting authority.

No matter what the arbitration court decides, further problems are to be expected.

If the company mentioned fails, you have to expect a lawsuit, which in turn leads to delays - delays that are particularly bitter in Olching's case because the district has rented the alternative containers and has to pay for them.

The next lawsuit

According to Tagblatt-Info, there is also another very big imponderable: If the company with the cheapest offer prevails despite opposition from the district, a lawsuit from the second cheapest bidder can be expected.

According to Tagblatt information, he is convinced that the tender winner's offer is far too cheap ("underbid") and therefore completely unrealistic.

My news

  • Shocking moment: 23-year-old hits dog - owner becomes suspicious and goes to the police station

  • Hearty sayings and yoga at the strong beer festival reading

  • Farmers celebrate a hearty double anniversary reading

  • A8 closed after serious accident: BMW crashes into gritting vehicle - wreck immediately catches fire

  • Asylum accommodation: Mayor promotes reading for understanding

  • “Chest Pain Unit” in the Fürstenfeldbruck Clinic receives certificate reading

The district is therefore faced with a dilemma – and another annoying construction site with unforeseeable financial consequences.

The current estimates for the renovation of the high school are already at 84 million euros.

Static problems with the containers led to initial delays.

Officially, the district office only wants to confirm that a bidder has submitted an application for review and the matter is now with the public procurement chamber.

An award is currently not possible due to the ongoing proceedings.

The entire procurement process is subject to the principle of secrecy until the contract is awarded.

Four reasons why public building is almost unaffordable

In a more general form, the problem of public building was now also a topic in the district committee of the district council.

Johann Wörle (CSU), member of the building commission, named four reasons under the “Miscellaneous” section as to why building has become so expensive.

One of the reasons is the “primitive construction method” and mediocre architectural achievements 50 years ago.

This old problem is now practically falling on one's feet.

Wörle: “That annoys me the most.”

Another reason for the development, according to Wörle: the high requirements for fire protection and statics.

Only the Pope is apparently still above these demands, said Wörle, not without sarcasm.

Next problem: Procurement law and of course the general, current situation, which cannot be changed.

Wörle raised the question of whether it would not be better to build long-lasting and easy-care buildings instead of building “primitive buildings that are susceptible to repairs”.

In this context, Olching's mayor and SPD district councilor Andreas Magg repeated his doubts about the current decision regarding high schools and quoted Wörle.

“Why did we decide to renovate a 'primitive building'?” Perhaps it would have been better to build new, thought Andreas Magg.

On this issue, however, the district administrator emphasized some time ago that this would have been even more expensive.

st

comment

It cannot be true that the administration and district council, against their better judgment, are practically forced to hire a company with which they have had the worst experiences.

If a relationship of trust is broken, the district council must have the opportunity to react accordingly.

Procurement law - of course it is justified in principle - reduces itself to absurdity here: it lets the public sector run straight into the open and does nothing about it.

It would definitely make sense if local politicians had more leeway when making procurement decisions than is apparently the case now.

Because practically everyone brings a lot of experience with them.

Be it from their work at the district level or from their work in city and local councils.

Leaving such knowledge unused is negligent.

We wish those responsible for the renovation of the high school good nerves.

Because of course they will be met with scorn, ridicule and criticism - which they do not deserve given the legal procurement framework.

(st)

You can find even more current news from the Fürstenfeldbruck district at Merkur.de/Fürstenfeldbruck.

Source: merkur

All news articles on 2024-02-26

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.