Ruderatshofen railway crossing closes: Exact time now known

2024-03-18T10:16:12.490Z

Highlights: Ruderatshofen railway crossing closes: Exact time now known.. As of: March 18, 2024, 10:56 a.m By: Felix Gattinger CommentsPressSplit The old railway crossing in Ruderatshofe is currently experiencing its last days. When the barriers close for the last time on March 22nd at around 7:30 a. m., the old local connection will also be history. Residents of Hiemenhofen and the residential road “Am Bahnhof” will be redirected via Apfeltrang to the new bypass until the end of May.



As of: March 18, 2024, 10:56 a.m

By: Felix Gattinger

Comments

Press

Split

The Ruderatshofen railway crossing shortly before its closure.

© Photo: Gattinger

The railway crossing between Ruderatshofen and its Apfeltrang district will close on Friday, March 22nd at 7:30 a.m., the Ostallgäu district office has just announced.

This is also the end of the direct connection between the two districts.

But that's not all, reports the Ostallgäu district office.

Ruderatshofen

– The old railway crossing in Ruderatshofen is currently experiencing its last days.

When the barriers close for the last time on March 22nd at around 7:30 a.m., the old local connection between Ruderatshofen and its Apfeltrang district will also be history.

As a result of this change against the background of the new local bypass, there will also be further changes.

Ruderatshofen level crossing closes: exact time now known - local connection cut off - remaining work until the end of May

The final construction work is currently underway on the new community connection road between the Hiemenhofen district and the future connection to the new bypass in the area of ​​the new railway underpass.

This road is scheduled to be completed in April.

Ruderatshofen level crossing closes: exact time now known - local connection cut off - remaining work until the end of May

Residents of Hiemenhofen and the residential road “Am Bahnhof” will be redirected via Apfeltrang to the new bypass until this construction work is completed.

It is expected that by the end of May, some remaining work under traffic will be completed in the entire construction site area of ​​the new and old district road OAL 7 using traffic light control.

In its press release, the Ostallgäu district asks all local road users and residents to understand that there will be disruptions during the construction work.

Adjustments to the closure period due to weather cannot currently be ruled out.

Source: merkur

All news articles on 2024-03-18

You may like

Trends 24h

Latest

© Communities 2019 - Privacy

The information on this site is from external sources that are not under our control.
The inclusion of any links does not necessarily imply a recommendation or endorse the views expressed within them.