Al-Hasakah-Sana
A technical breakdown on the 230-Tabqa-Al-Bawab line led to power cuts in large areas in the cities and rural areas of al-Hasakah governorate.
Anwar al-Akleh, General Manager of Hasakeh Electricity Company, told SANA that a technical failure occurred last night on the line in the area near the Tabqa Dam in Raqqa countryside. Vital in the province such as hospitals, mills and bakeries currently produced quantities from the Swedish power plant.
It is noteworthy that the province of al-Hasakah was fed on an additional power line is 230 October - Mabrouka, but he left the service as a result of being targeted by the Turkish aggression.